Paddington Station. Eight drawings on one sheet. Drawings are of elevation from booking hall and various sections including plan of stanchion head. Drawing is signed by WW Grierson, Sleabold and Hunt and Son.
15 September 1904
Paddington Station. Three drawings on one sheet. First drawing is of an elevation, second drawing is of a plan, third drawing is of detail of ring handle. Drawing is signed by Grierson, and contractors A Jackman and Son on 23rd April 1906 and a witness.
19 February 1906
Paddington Station. New extension of office over Royal Waiting Room. Three drawings on one sheet. First drawing is of section on line AB, second drawing is of section on line CD, third drawing is of plan of 1st floor. Drawing is signed by Grierson.
20 February 1904
Paddington Station. New season ticket office. Three drawings on one sheet all of screen details for new season ticket office.
1904-1906
Paddington Station new season ticket office. Thirteen drawings on one sheet. Drawings are of elevations of deal screen, floor plans, various sections and an elevation of oak screen. Drawing is signed by WW Grierson, Sleabold and Hunt and Son.
17 December 1904
Paddington Station Alterations. Ten drawings on one sheet for details of new main roof. Drawings include plans of roof and details and sections. Drawing is signed by Ralph Holliday for Holliday and Greenwood.
28 April 1914
Paddington Station Alterations. Seven drawings of details of new main roof. Drawings include details and cross sections. Drawing is signed by Ralph Holliday for Holliday and Greenwood.
28 April 1914
GWR Paddington Station. Plan showing showing details of the foundations, drainage etc under the passenger station as well as the track layout.
23 August 1916
Paddington Station Additional Offices. Ten drawings on one sheet. Drawings include elevations and plans of girders, cast iron shoes and plan. Drawing is signed by Lancaster O[wen].
05 June 1878
Drawing of timbers for permanent way on departure lines, plan, section and elevation
7th December 1853
Drawing of skylights within the railings in the passage under the rails between the arrival and departure platforms; calculations on the reverse
1853
drawings for a truck for carrying luggage from the hotel to the station, including plan, general plan, elevation and section
14th September 1854
Cross sections of the departure line to the second platform, and the second arriival platform
1854
Drawings showing retaining walls and approach walls between Ranelagh Bridge and Black Lion Road Bridge Paddington
January 1856
Drawings of the rods to tie the new span of roof at Paddington station, including plan, part-plan, elevation, sectional plan and details
1915
Outside elevation, plan on top and details of the new roof end screen
December 1914 to 23rd February 1915
Drawings of turnbuckles, linkplates and spanners for alterations at Paddington Station, with required numbers for each item
27th - 30th July 1915
Elevations of rib C and F, and plans of stay rods to the column side
July 1915