Drawing of section of roof between the new building and screen, and the roof between the existing wall and new buildings
March 1889 to 16th April 1889
4 drawings on one sheet showing plan elevation and section of incline and steps to footbridge on island platform
March 1889
Plan and drawings of the stairs and incline on the existing platform, with sections through staircase and incline walls
March 1889 to 16th April 1889
Drawings of refreshment room on the Island Platform at Chester Station - basement, ground and first floor plan
March 1889 to 16th April 1889
Drawings of the rearrangement of Chester station - corss sections of 47 and 39 feet span roofs
March 1889 to 16th April 1889
General plan of the footbridge, staircases and inclines at the centre of the station
March 1889 to 16th April 1889
Drawing of a new Island platform - general plan, elevation of existing wall, elevation of ramp, section on line and section of manhole
March 1889 to 16th April 1889
5 drawings on one sheet showing elevations, section and plans of left luggage office on existing platform
March 1889
Drawings for the gider for the footbridge in the centre of the platform
March 1889 to 16th April 1889
Drawings of refreshment rooms and kitchen at Chester Station, sections and elevations
March 1889 to 16th April 1889
6 drawings on one sheet showing elevations and sections of waiting rooms &c
March 1889
Drawings of stairs and incline on existing platform, elevation of door and window to stationmaster's office, elevation to central platform, sections.
March 1889 to 16th April 1889
Drawings of Refreshments rooms and kitchen, including longitudinal section, Elevation, transverse section, Cross section through stairs, elevation of kitchen and store windows and door to parlour stairs, and cross section through manhole
March 1889 to 16th April 1889
Drawings of details of ironwork and columns to glazed screen, with construction notes
March 1889 to 16th April 1889
General plan of footbridge, staircases and inclines at the centre of Chester Station, existing work in black lines, new work in red lines
March 1889 to 16th April 1889
5 drawings showing plans sections and elevations of glazed screen
March 1889
Chester Station Rearrangement, Plan of Roof, with signatures
16th April 1889
Drawings of details of staircase to the footbridge at the Crewe end of the station, including plan, sections, and half plan,